1.1 Which step of SDLC performs cost-benefit analysis?
A) Coding
B) Testing
C) Design
D) None of the above
1.2 Project planning is done by
A) Gantt
B) State visits
C) Spiral Model
D) COCOMO

1.3 Which of the following is not a tool for data collection?
A) On-site observations
B) Program flowcharts
C) Interviews
D) Questionnaires
1.4 An ER diagram represents
A) Entities
B) Keys
C) Relationship
D) All of the above
1.5 Prototyping means
A) creating, developing and refining a working model of the operational system
B) testing the computer system
C) designing the computer system
D) none of the above
1.6 COCOMO stands for
A) Cost Constructive Model
B) Constructive Cost Model
C) Common Cost Model
D) None of the above
1.7 A DBMS is
A) another name for database systems
B) independent of a database
C) dependent on application programs
D) a set of procedures which manage a database
1.8 CASE stands for
A) Computer Aided Software Engineering
B) Component Aided Software Engineering
C) Cost Analysis Software Engineering
D) Computer Application & Software Engineering
1.9 Glass Box Testing is also known as
A) White box testing
B) Black box testing
C) A) and B) both
D) None of the above
1.10 A DFD specifies
A) Different processes that the system performs
B) Data interchange among the processes
C) A) and B) both
D) None of the above

2. Each statement below is either TRUE or FALSE. Choose the most appropriate one and ENTER in the “OMR” answer sheet supplied with the question paper, following instructions therein. (1x10)

2.1 A data dictionary is used for spelling checks in Word Processor.
2.2 White-box testing can be started after installation.
2.3 A Database Administrator is the one who analyze the database for an application.
2.4 Interoperability is a desirable characteristic of a good system design.
2.5 Beta testing refers to the system testing carried out by the test team within the developing
organization.
2.6 MIS stands for Management Information Security.
2.7 Design should be traceable to the requirement specifications.
2.8 Once we write the program and test it, the development work is not over.
2.9 Sandwiched Testing is one type of Integration Testing.
2.10 The physical connections between elements of the OO design represent coupling within an OO
system.

3. Match words and phrases in column X with the closest related meaning/word(s)/phrase(s) in column Y. Enter your selection in the “OMR” answer sheet supplied with the question paper, following instructions therein. (1x10)
                                   X                                                            Y
3.1 Process                                                               A. Functional Testing
3.2 Black Box Testing                                             B. Alpha Testing
3.3 White Box Testing                                            C. Planning Tool
3.4 Password                                                           D. Model
3.5 Pull down Menu                                               E. Critical Path
3.6 PERT Chart                                                      F. Glass Box Testing
3.7 The longest chain of activities in a project      G. Data Dictionary
3.8 Aggregation                                                    H. Part of relation
3.9 Prototype                                                       I. Selection of an option by an user
3.10 A structured repository of data                   J. Meta Data
about data is called
                                                                             K. Bubble
                                                                              L. Access control
                                                                             M. Is a relation

4. Each statement below has a blank space to fit one of the word(s) or phrase(s) in the list below. Enter your choice in the “OMR” answer sheet supplied with the question paper, following instructions therein. (1x10)

A. SRS                                       B. Module Testing                           C. Branch Testing
D. Integration Testing                E. Control Flow Graph                   F. Delphi Cost Estimation
G. Cohesion                                H. Coupling                                    I. User Interface
J. Expert Decision Technique      K. Brainstorming L. Bar              M. Common Coupling

4.1 The ________ contains all the user requirements in an informal form.
4.2 The ________ of software is responsible for all interactions with the user.
4.3 Unit testing is known as ________.
4.4 A linearly independent path can be defined in terms of ________.
4.5 Edge Testing is also known as ________.
4.6 In a good design, the modules should have low ________.
4.7 ________ is one of the Empirical Estimation Techniques.
4.8 A Gantt chart is fundamentally a ________ chart.
4.9 Interviews and ________ may be used to elicit information regarding the user’s requirements.
4.10 If two modules share some global data items then this type of coupling is known as ________.

PART TWO
(Answer any FOUR questions)
5.
a) Explain the role and responsibilities of a system analyst.
b) Elaborate the concepts of Coupling and cohesion and their types in reference to modular design
approach.
(6+9)
6.
a) Explain alpha testing and beta testing.
b) What are the characteristics of a good design?
c) What do you mean by SDLC? Describe the different phases of SDLC?
(4+4+7)
7.
a) Compare the Object-Oriented approach with Module Oriented Approach.
b) Explain different data and fact gathering techniques.
(6+9)
8.
a) Explain different types of Information System in an organization.
b) Differentiate between Verification and Validation.
(9+6)
9. A supermarket needs to develop the following software to encourage the regular customer. For
this, the customer needs o supply his residential address, telephone number, and the driving
license number. Each customer who registers for this scheme is assigned a unique customer
number (CN) by the computer. A customer can present his CN to the check-out staff when he
makes any purchase. In this case, the value of his purchase is credited against his CN. At the
end of each year, the supermarket awards surprise gifts to 10 customers who make the highest
total purchase over the year. Also, it awards a 22 carat gold coin to every customer whose
purchases exceed Rs. 30,000. The entire values against the CN are reset on the last day of
every year after the prize winners’ lists are generated.
a) Draw the DFD for above defined Supermarket Prize Scheme.
b) Draw the Use Case Model for above defined Supermarket Prize Scheme.
(9+6)